Friday, February 14, 2014

Bunker renovation schedule

VM golf services is currently on schedule to finish the project next Sunday.  They have 11 bunker floors completed with the gravel layer.  The polymer coating has been scheduled for Tuesday and will take the entire day to complete.  Half the sand will be delivered this Monday and will be ready for installation on Wednesday morning. We are extremely excited to see the finished product.  Below is a picture of the gravel layer on #11 greenside bunker.

This new Better Billy Bunker designed will eliminate contamination during hard rains as seen in the picture below.  



Wednesday, February 12, 2014

Gravel Layer

We are in the second stage of the bunker project.  Below are some pictures of VM installing the gravel layer into the floor of the bunker. Once all 18 bunkers are complete Forefront Construction will spray the polymer coating.  


Sunday, February 9, 2014

Sundays bunker update

VM has complete stage one of the bunker project.  On Monday we will begin removing the top layer of gravel to expose the existing drainage tile. Drains will be flushed and all damaged drains will be replaced.  We will also be adding extra lines to bunkers that have drained poorly in the past.  I expect all drain work to be completed within two days.  The next step is to added the gravel blanket.  

Friday, February 7, 2014

Bunker Update

It is day four of the bunker project and VM Services has cleaned ten of the eighteen bunkers.  I expect the initial stages of this project to be completed by the end of the weekend.  On Monday, our staff will start checking the existing drain lines and determine what needs to be replaced.  Once drains are in working order, VM will begin adding 2" of gravel to the bunker floor.  This gravel will then be sprayed with a polymer to hold the gravel together. The spraying process will be preformed by a certified applicator.  Please check out http://billybunker.com/ for more details.

Wednesday, February 5, 2014

Blue Nine Bunker Project

I would like to officially welcome VM golf services to April Sound and I'm looking forward to working with them over the next few weeks. We are in the initial stages of the process which includes removal of the contaminated sand and expose the bunker floor.  Once the floor is exposed, they will begin inspecting the drainage tiles.  VM will make sure all drains are in working order before we start the "better billy bunker" process. Over the next few weeks, I'll be posting pictures and updates of the project and a quick summary of how this process works. Below are a few pictures of the bunker floor on number #12 green.
 

Thursday, June 13, 2013

#12 Fairway Bunker

We finished the fairway bunker on number 12 today.  Below is a picture of the finished project.